Search This Blog

Tuesday, November 17, 2015

How to change ADFS token life from default 60 to 240 minutes

How to change ADFS token life from default 60 to 240 minutes:

Set-ADFSRelyingPartyTrust -Targetname "relying_party" -TokenLifetime 240

Saturday, November 14, 2015

Altigen MaxACD 6.5 and AMD CPU

Altigen supports only Intel processor. However, we have successfully tested MaxACD in VMWare Virtual machine in a host with AMD Opteron processor.

Wednesday, November 11, 2015

Some help for Lync, SFB designers

https://skypevalidator.com

SFB conversations in mobile and Desktop are different?

http://ucmart.uk/2015/06/15/skype-for-business-enable-server-side-conversation-history/

MS Project - task types

All is turning around a simple formula:

W =  U * D

where W - work, U - units (number of resources for the task), D - duration.

Task types can be Fixed Work, Fixed Units, Fixed Duration.


Most used is Fixed Work.

If you have 32h of Work and it is fixed, you need 1 person (8h working day) and 4 days then duriation. If you add additonal resource, now you have say 2 persons - then duration will be 2.


Now if you would set task as Fixed Duration and you add second person, MSP will change Work, not duration (because it is fixed). It is less intuitive, but once you have formula and mind and you know which variable is fixed, then all become clear.

Fixed units is also a task type, and guess what - the same formula applies.  Can not change unit then. By changing duration to 2 you will half the work to 16. The same MPS person can only do half of the work if you ask him to half duration.

Tuesday, November 3, 2015

What's new in SharePoint 2016

http://en.share-gate.com/blog/whats-new-in-sharepoint-2016

5000 items limit removed
10gb files upload
Hybrid nature

SfB client login process

http://skype4b.uk/2015/11/03/skype-for-business-client-sign-in-workflow-chart-external/